Connection procedure
Connecting to the Danish grid is non-discriminatory from a RES viewpoint. Energy suppliers must comply with Commission Regulation (EU) 2016/631, as well as requirements set out by the Ministry of Climate, Energy and Utilities and the Danish transmission grid operator (Energinet).
Rules concerning the connection of a new producer to the grid
There are specific standards defined in the Electricity Supply Act that need to be met to connect to the grid, such as providing electricity with a certain voltage and frequency.
Rules for connecting RES and storage to the grid
RES plants need to meet certain standards, just like any other energy production plant, to be connected to the grid. The DSO can set additional technical requirements.
Access to electricity from renewable energy sources to the grid is mainly governed by the general legislation on energy and shall be granted according to the principle of non-discrimination. Electricity from renewable sources is subject to special provisions only with regard to the use of the grid, in which renewable energy shall be given priority. If having more than 1 MW of storage, a producer can offer balancing of the grid and get paid for it.
A new producer charge for renewable energy production plants was introduced on January 1st 2023. One part of the charge is a station fee for production plants that are connected to the transmission network and a transformer fee for production plants that are connected to the distribution level. Another part of the charge is the standard grid connection fee, through which producers will be contributing to the necessary grid development.
The Electricity Supply Act does not provide any details on the connection to the Danish grid, but leaves this to the Ministry of Climate, Energy and Utilities to specify. In general, the process to gain access to the Danish TSO energy grid consists of four steps:
- Preparation;
- Current setting permit (EON);
- Temporary operation permit (ION); and
- Final operation permit (FON).
Furthermore, the plant must comply with the Commission Regulation (EU) 2016/631. Preparation in the preparation stage, plant developers must provide documentation to their grid operator on the proposed plant to connect to the Danish grid. Then, a decision is taken by the grid operator and Energinet on whether the plant will be connected to the distribution grid or the transmission grid. A second part concerns the concretisation of the project between the plan owner and Energinet, which can take up to 3.5 years. In this part, the plant owner and Energinet discuss any changes that need to be made to the plan or to the grid (e.g., expanding the capacity of the grid in the area of the proposed plant). Finally, the plant owner and Energinet conclude a contract for the building of the plant. Current setting permits. Once the plant is constructed, the plan owner must apply for a current setting permit (EON). Temporary operation permit. The plant owner must provide documentation that the plant complies with EU rules on power generators and a plan for the testing phase of the power plant. The temporary operation permit (ION) may be issued for a period of a maximum of 2 years. The plant owner conducts the necessary tests, and Energinet reviews the results to ensure compliance with standards. Final operation permit If the testing phase results in a pass, Energinet will issue a final operation permit (FON). For connection to DSOs, the procedure varies depending on the DSO. However, in general, the procedure requires pre-approval from the DSO and a building permit from the municipality, then a positive reply from the DSO. Once the installation is complete according to the specifications given in the pre-approval form, the installer requests the final approval from the DSO. Approval process The approval process for connection to a DSO requires that the RES installation owner contacts a certified installer who fills out the pre-approval form from the DSO, as well as the RES specification and data form from Dansk Energi (lobby organisation for Danish energy companies). Installation and connection to the grid. The installer constructs the RES installation and notifies the DSO of the construction, who will install a meter at the RES installation and connect it to the grid. After which, the RES installation will be in operation.
Specifications for islands, isolated grids, microgrids, local grids, etc.
There are no specifications.
Exceptions
There are no measures on energy sharing or energy communities in Denmark, as legislation does not currently support the sharing of electricity between individuals. However, a scheme which supports local citizen initiatives to secure loan guarantees for feasibility studies of RES plants does exist in Denmark [2]. Though this does not extend to sharing energy or creating energy communities, as the support no longer applies past the planning stages. On the other hand, a measure on net-metering allows for prosumers to pay a reduced charge on electricity produced from their own solar panels or wind generators, as long as the electricity is consumed within the hour. The Ministry of Climate, Energy and Supply can create special regulations for prosumers and energy communities regarding participation in the electricity market, consumption, production, storage, and rules on balancing responsibilities based on the EU’s Electricity Market Directive.
Possibilities to differentiate RES in scale and technology
In recent years, a shift has been made from technology-specific support to a higher degree of technology neutrality and a more market-based approach, through, e.g., multi-technology tenders. Support for certain technologies (e.g. biomass) has also been phased out recently.
In 2023, a new producer charge was introduced. This charge requires renewable energy producers to contribute to grid development through station and transformer fees.