Description of the process
Production units may be connected to the grid only after an inspection of the plant is carried out by an institution accredited by DGEG. After the compliance with the rules has been attested and the developer has concluded a contract for the acquisition and sale of the energy produced with the Retailer of Last Resort, then a certificate of exploitation is granted and the plant is connected to the grid (art. 20-B DL 76/2019).
-
Competent authority
- Distribution System Operators
- Directorate-General of Energy and Geology (DGEG)
- Energy Services Regulatory Authority (ERSE)
- Retailer of Last Resort
-