Electricity production license process

Abbreviated form of legal source

  • Law 24/2013
  • RD 1955/2000

Description of the process

When the RE installation is already built, project developers shall apply for an electricity production license, also called commissioning certificate (article 53, Law 24/2013). Without this certificate the plant cannot start feeding electricity into the grid.
The project developer shall apply for the license accompanying a certificate of completion of the work signed by a competent technician (RD 1955/2000).
For rooftop PV the regulation can vary according to the Autonomous Communities, but generally an exploitation license is not required when the self-consumption units up to 100 kW of installed power. In these cases, the installer of the unit will issue a certificate of the installation instead.

Competent authority

  • MITECO
  • Autonomous Communities
  • Industry and Energy Departments of the National Government Delegations

Technologies

Wind energy onshore

Relevant

Wind energy offshore
Solar energy

Relevant

Solar Thermal
Geothermal energy
Geothermal energy
Aerothermal
Hydrothermal
Hydro-power
Biogas
Biogas
Biomass