Skip to main content
European Commission logo
Clean energy for EU islands
  • Regulatory information
  • Electricity support

Feed-in tariff

  1. Abbreviated form of legal source(s)

    • DL 76/2019
    • Ordinance 80/2020
  2. Description of support scheme

    Electricity producers from renewable energy resources are entitled to receive fixed prices for the energy they produce. This price may be either fixed or indexed according to a referential value – with or without minimum or maximum amounts (art. 4 of DL 76/2019).
    Operators of Small Grid Feed-in Unit (Unidade de Pequena Produção – UPP) with installed capacity of ≤ 1 MW (art. 4 of DL 76/2019) receive a fixed amount defined by the government, until the quota, annually defined by the government, is reached.

  3. Amount

    The guaranteed remuneration can be granted to producers who own a UPP, via the allocation of a fixed price decided, which is decided through a bidding process (whose reference will be the amount set by the government in previous ordinances. For instance, in 2020, the government approved a price of 45 euros per MWh and a maximum quota of 20MW [art. 2 and 3 of Ordinance 80/2020]) or based on the median of prices established by the last tender procedure (art. 4 of DL 76/2019).

  4. Addressees

    Electricity producers that fit into the renewables’ special regime (i.e., RES-E producers).
    Special regime production (Produção em Regime Especial, PRE, in Portuguese) consists of a set of electricity production technologies from renewable sources, such as wind, water, sun, biomass and the sea, and high energy efficiency technologies, such as the combined production of heat and electricity – cogeneration.

  5. Procedure

    Plant operators who fit into the UPP category may join the guaranteed regime via registration of the unit on the SERUP Portal.

  6. Competent authority

    • Energy Services Regulatory Authority (ERSE).
    • Directorate-General of Energy and Geology (DGEG).
  7. Technologies

    Wind energy onshore

    Eligible up until 1 MW of installed capacity

    Wind energy offshore

    Eligible up until 1 MW of installed capacity

    Solar energy

    Eligible up until 1 MW of installed capacity

    Geothermal energy

    Eligible up until 1 MW of installed capacity

    Biogas

    Eligible up until 1 MW of installed capacity

    Hydro-power

    Eligible up until 1 MW of installed capacity

    Biomass

    Eligible up until 1 MW of installed capacity