Electricity production license process

  1. Abbreviated form of legal source

    Electricity Supply Act

  2. Description of the process

    Electricity production from all plants with a capacity of more than 25 MW requires a license to produce electricity. To obtain this license, applicants must prove that they have the necessary technical and financial capacity. The license is granted by DEA for at least 20 years (Electricity Supply Act).

  3. Competent authority

    DEA

  4. Technologies