Abbreviated form of legal source

S.L. 545.13

Procedure

The distribution system operator is responsible for developing the transmission and distribution grid infrastructure and for the further development of electricity production from RES (Art. 25 S.L. 545.13)
The construction of new grid capacity is always authorised through a tendering procedure or any equivalent procedure in terms of transparency and non-discrimination (Art. 12 S.L. 545.13).
A tender for new capacity may be launched by a public body or a private body independently from electricity generation, distribution and supply activities, appointed for the purpose by the Minister by notice in the Gazette. (Art. 12 S.L. 545.13).